News in brief

26 April 2017

Tarralla Creek Trail – Shared Path Reconstruction

Long View Road, Croydon South

Council will be undertaking reconstruction/realignment of the shared path, installation of retaining wall and fence to improve safety and visibility.

Works will start Monday 1 May and are expected to take six weeks to complete, subject to weather conditions.

Road Rehabilitation

Dublin Road - between Mt Dandenong Rd and Patterson St, Ringwood East

The works will include the reconstruction of kerb, vehicle crossings, pavement and asphalt overlay, including signage and line marking upgrades.

Works will start Wednesday 26 April and are expected to take about 14 weeks, subject to weather conditions.

Traffic controls will be in place as works progress, although we will endeavour to minimise delays as much as possible.

Lusher Road Drainage Improvement

Lusher Road - between Birdwood Rd and No 35 Lusher Road, Croydon

Works will include the reconstruction of Lusher Road, installation of significant drainage infrastructure and flood mitigation works. Once completed there will be an improvement in the amount of stormwater captured and greater protection of local properties from flooding during heavy storm events.

Works will start on Monday 1 May and are expected to be completed in June, subject to weather conditions.

Please be advised that between 1 May to 22 May, the road will be closed at 23 Lusher Road (from 7am-5pm) to facilitate major drainage works. A detour will be in place via Vinter Avenue, Bayswater Road and Mt Dandenong Road.

Outside working hours, Lusher Road will be partially closed (one lane) and will operate under portable traffic signals.

For more information on the progress of council works, visit www.maroondah.vic.gov.au/CurrentWorks.aspx



Main Navigation